(2023) AACE-PSP Exam Dumps, Practice Test Questions BUNDLE PACK AACE Certification Certification AACE-PSP Sample Questions Reliable To be eligible for the AACE-PSP certification, candidates must have a minimum of four years of professional experience in planning and scheduling. They must also have a bachelor's degree or higher in engineering, construction management, business administration, or a related [...]

(2023) AACE-PSP Exam Dumps, Practice Test Questions BUNDLE PACK [Q46-Q67]

Share

(2023) AACE-PSP Exam Dumps, Practice Test Questions BUNDLE PACK

AACE Certification Certification AACE-PSP Sample Questions Reliable


To be eligible for the AACE-PSP certification, candidates must have a minimum of four years of professional experience in planning and scheduling. They must also have a bachelor's degree or higher in engineering, construction management, business administration, or a related field. Alternatively, candidates with eight years of professional experience in planning and scheduling can also apply for the certification without a bachelor's degree.


AACE International is a renowned professional organization that provides certifications and training for professionals in the field of project management, cost engineering, and scheduling. One of the most popular certifications offered by AACE International is the AACE-PSP (Planning & Scheduling Professional) Certification Exam. Planning & Scheduling Professional (PSP) Exam certification is designed to validate the skills and knowledge of individuals who are involved in project planning, scheduling, and control.

 

NEW QUESTION # 46
What problems can a soils engineer deal with on a project?

  • A. Toxic soils.
  • B. Archeological findings.
  • C. Hidden subsurface conditions.
  • D. Survey error.

Answer: C


NEW QUESTION # 47
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

  • A. There is no such thing.
  • B. It is calculated using logic reflecting out-of-sequence progress.
  • C. It is calculated using the original logic.
  • D. An out-of-sequence activity cannot resume until all predecessors are finished.

Answer: C


NEW QUESTION # 48
Determine the correct formula and date for the late finish for Activity 2002.

  • A. LS.2003 - 1 day -> 11.06.01.
  • B. LS.2003 - 1 day -> 10-06-01.
  • C. LS.2003 + 1 day -> 10-07-01.
  • D. LS.2003 - 1 day -> 10-05-01.

Answer: D


NEW QUESTION # 49
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

  • A. The schedule has too much detail to reflect an accurate critical path.
  • B. Different calendars are assigned to certain activities in the logical chain.
  • C. Certain activities in the critical path have no successors.
  • D. The schedule is projecting an "early completion".

Answer: C


NEW QUESTION # 50
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

  • A. Not suitable for complicated projects with multiple planned critical paths.
  • B. Less accurate as the analysis advances through the project.
  • C. Accuracy is increased by inserting delaying events into the as-planned schedule.
  • D. Not suitable for projects with long durations.

Answer: C


NEW QUESTION # 51
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

  • A. EF.11001 + 1 day.
  • B. 02-19-04.
  • C. LS.11001 + 25 days.
  • D. EF.11001.

Answer: B


NEW QUESTION # 52
What is the relationship depicted between Activity G and Activity H?

  • A. You cannot tell with the supplied information.
  • B. Finish-to-finish.
  • C. Start-to-start.
  • D. Finish-to-start.

Answer: C


NEW QUESTION # 53
What owner action could have mitigated the late completion of the project?

  • A. Prepare better structural steel drawings.
  • B. Use a procurement agent to monitor and expedite equipment deliveries.
  • C. Hire a more senior project manager.
  • D. Self-perform more of the work.

Answer: B


NEW QUESTION # 54
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

  • A. 09-18-01.
  • B. 09-28-01.
  • C. 09-08-01.
  • D. 09-15-01.

Answer: C


NEW QUESTION # 55
In a "crashed" schedule, which is a chain of activities that precede activity 2004?

  • A. 1001, 2002, 2003
  • B. 2001, 2002, 2003, 2007
  • C. 1001, 2001, 2002, 2003
  • D. 1001, 2002, 2002, 2003, 3001

Answer: C


NEW QUESTION # 56
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

  • A. Has yet to be completed.
  • B. It is on the critical path.
  • C. Was completed in the past.
  • D. Is a milestone.

Answer: A


NEW QUESTION # 57
Free float is the

  • A. Amount of time the early start of an activity can be delayed without impacting the early start of the successor activity.
  • B. Difference between the early dates and late dates of an activity.
  • C. Difference In float value of the critical path activities and the float value of the specific activity being analyzed.
  • D. Difference between the early finish dates and late finish dates of an activity.

Answer: A


NEW QUESTION # 58
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

  • A. 02-19-04
  • B. 03-11-04
  • C. 03-20-04
  • D. 03-21-04

Answer: B


NEW QUESTION # 59
Determine the correct formula and date for the late start for Activity 9001.

  • A. LF.9001 Dur.9001 -> 11-20-02.
  • B. There is insufficient data provided to calculate the answer.
  • C. The early finish is required in order to determine the answer.
  • D. LS.6001 Dur.6001 -> 11-20-02.

Answer: A


NEW QUESTION # 60
At a minimum, periodic reporting must be done at what interval?

  • A. Monthly.
  • B. As requested by the owner.
  • C. As requested by the project manager.
  • D. As specified in the contract documents.

Answer: D


NEW QUESTION # 61
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

  • A. 407 days
  • B. 255 days
  • C. 362 days
  • D. 267 days

Answer: A


NEW QUESTION # 62
Is activity 7001 pictured correctly in the precedence diagram?

  • A. No, the start-to-start and finish-to-finish relationships are backwards.
  • B. Yes, the duration is 48 days.
  • C. No, the total float is not shown correctly.
  • D. Yes, except the early finish date is not shown.

Answer: B


NEW QUESTION # 63
The activity with the most total float is:

  • A. Activity D.
  • B. Activity F.
  • C. Activity I.
  • D. Activity C.

Answer: C


NEW QUESTION # 64
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?

  • A. 18 work days
  • B. 7 work days
  • C. 8 work days
  • D. 15 workdays

Answer: C


NEW QUESTION # 65
What is a key first step in developing a critical path method schedule?

  • A. Setting out the resource to be used and its limitations.
  • B. Drawing a bar chart of the key phrases of the work.
  • C. Defining the execution plan to meet the required scope of work.
  • D. Drawing the logic diagram.

Answer: D


NEW QUESTION # 66
Budgeted cost of work scheduled is _______________________.

  • A. The total authorized budget for accomplishing the project scope
  • B. The sum of all budgets for work scheduled to be accomplished within a given time period
  • C. The expected total cost of an activity, group of activities or the project
  • D. The value of the completed work expressed in terms of the budget assigned to that work

Answer: C


NEW QUESTION # 67
......


AACE International is a professional association for cost engineering, project management, and planning and scheduling professionals. The association offers a range of certifications to its members, including the AACE-PSP (Planning & Scheduling Professional) certification. The AACE-PSP certification is designed for individuals who are involved in planning and scheduling activities for projects and programs. Planning & Scheduling Professional (PSP) Exam certification program is recognized worldwide and is considered a benchmark for planning and scheduling professionals.

 